Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
18 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
17 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
16 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
13 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
12 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
11 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
10 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
09 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
07 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE |