Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Feb 2023 |
Work in progress | 20% Completed | 10/02/2023
Various dia of DI and HDPE pipes are supplied on site 23.729 KM laid/out of 113km 1. 90mmHDPE -19422m 2. 110 mm HDPE -1272.10 m 3. 160mm HDPE -1099 m ,4. 140mm pvc -1888.00m,5. 80 mm GI -56.10M |
Chittur Project Dn - AE 4 |
|
03 Feb 2023 |
Work in progress | 16% Completed | 03/02/2023
Various dia of DI and HDPE pipes are supplied on site 19.606 KM laid/out of 113km 1. 90mmHDPE -15761 m 2. 110 mm HDPE -822.10 m 3. 160mm HDPE -1099 m ,4. 140mm pvc -1888.00m,5. 80 mm GI -44.10M |
Chittur Project Dn - AE 4 |
|
30 Jan 2023 |
Work in progress | 16% Completed | 30/01/2023
Various dia of DI and HDPE pipes are supplied on site 18.177 KM laid/out of 113km 1. 90mmHDPE -14359.50 m 2. 110 mm HDPE -822.10 m 3. 160mm HDPE -1099 m ,4. 140mm pvc -1888.00m,5. 80 mm GI -15.65M |
Chittur Project Dn - AE 4 |
|
20 Jan 2023 |
Work in progress | 5% Completed | 20/01/2023
Various dia of DI and HDPE pipes are supplied on site 12.479 KM laid 1. 90mmHDPE -11170.50 m 2. 110 mm HDPE -822.10 m 3. 160mm HDPE -403m ,4. 140mm pvc -90m |
Chittur Project Dn - AE 4 |
|
13 Jan 2023 |
Work in progress | 3% Completed | 13/01/2023
Various dia of DI and HDPE pipes are supplied on site and LSGD road restoration Estimate submitted on sugama portal, 8.887 KM laid 1. 90mmHDPE -7578.50m 2. 110 mm HDPE -822.10 m 3. 160mm HDPE -403m ,4. 140mm pvc -90m |
Chittur Project Dn - AE 4 |
|
05 Jan 2023 |
Work in progress | 3% Completed | 05/01/2023
work started on 21.12.2022 ,various dia of DI and HDPE pipes are supplied on site and LSGD road restoration Estimate submitted on sugama portal, 6.55 KM laid 1. 90mmHDPE -5422m 2. 110 mm HDPE -779.70 3. 160mm HDPE -354 |
Chittur Project Dn - AE 4 |
|
30 Dec 2022 |
Work in progress | 3% Completed | 29/12/2022
work started on 21.12.2022 ,various dia of DI and HDPE pipes are supplied on site and LSGD road restoration Estimate submitted on sugama portal, 90mmHDPE AND 110 mm HDPE pipe laying work started,600 m laid |
Chittur Project Dn - AE 4 |
|
22 Dec 2022 |
work started on 21.12.2022 ,various dia of DI and HDPE pipes are supplied on site and LSGD road restoration Estimate submitted on sugama portal,90 mm HDPE pipe laying work started |
Chittur Project Dn - AE 4 |
|
09 Dec 2022 |
Work in progress | 2% Completed | 09/12/2022
Agreement executed ,various dia of DI and HDPE pipes are supplied on site and LSGD road restoration Estimate submitted on sugama portal |
Chittur Project Dn - AE 4 |
|
02 Dec 2022 |
Work in progress | 2% Completed | 02/12/2022
Agreement executed ,various dia of DI and HDPE pipes are supplied on site and LSGD road restoration Estimate submitted on sugama portal |
Chittur Project Dn - AE 4 |
|