Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jan 2024 Work in progress | 82% Completed | 24/01/2024 Various dia of DI and HDPE pipes are supplied on site 92.996 KM laid/out of 113km 1]. 90mmHDPE -74974.20m 2]. 110 mm HDPE -5308.10m 3]. 160mm HDPE -2060m, 4]. 140mm pvc – 3348.70 m, 5]. 80 mm GI -494.00 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-1633.85m 9)200mm DI-6M 10)250mm DI-2884.20M 11)FHTC 420/1816 NOS 12)500 mm DI-22M 13)400mm DI-217m Chittur Project Dn - AE 4
24 Jan 2024 Work in progress | 82% Completed | 24/01/2024 Various dia of DI and HDPE pipes are supplied on site 92.996 KM laid/out of 113km 1]. 90mmHDPE -74974.20m 2]. 110 mm HDPE -5308.10m 3]. 160mm HDPE -2060m, 4]. 140mm pvc – 3348.70 m, 5]. 80 mm GI -494.00 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-1633.85m 9)200mm DI-6M 10)250mm DI-2884.20M 11)FHTC 420/1816 NOS 12)500 mm DI-22M 13)400mm DI-217m Chittur Project Dn - AE 4
01 Dec 2023 Work in progress | 75% Completed | 01/12/2023 Various dia of DI and HDPE pipes are supplied on site 86.840 KM laid/out of 113km 1]. 90mmHDPE -70480.20m 2]. 110 mm HDPE -5093.10m 3]. 160mm HDPE -1678m, 4]. 140mm pvc – 3187.70 m, 5]. 80 mm GI -494.00 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-1633.85m 9)200mm DI-6M 10)250mm DI-2884.20M 10)FHTC 420/1816 NOS 11)500 mm DI-22M 12)400mm DI-217m Chittur Project Dn - AE 4
03 Nov 2023 Work in progress | 70% Completed | 03/11/2023 Various dia of DI and HDPE pipes are supplied on site 83.130KM laid/out of 113km 1]. 90mmHDPE -68143.50m 2]. 110 mm HDPE -5093.10m 3]. 160mm HDPE -1558m, 4]. 140mm pvc - 3093.20 m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-707.15m 9)200mm DI-6M 10)250mm DI-2884.20M 10)FHTC 420/1816 NOS Chittur Project Dn - AE 4
13 Oct 2023 Work in progress | 65% Completed | 13/10/2023 Various dia of DI and HDPE pipes are supplied on site 76.138KM laid/out of 113km 1]. 90mmHDPE -60531.50m 2]. 110 mm HDPE -5093.10m 3]. 160mm HDPE -1558m, 4]. 140mm pvc - 3093.20 m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M 10)FHTC 420/1816 NOS Chittur Project Dn - AE 4
30 Sep 2023 Work in progress | 63% Completed | 30/09/2023 Various dia of DI and HDPE pipes are supplied on site 74.966KM laid/out of 113km 1]. 90mmHDPE -59358.50m 2]. 110 mm HDPE -5093.10m 3]. 160mm HDPE -1558m, 4]. 140mm pvc - 3093.20 m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M FHTC 290/1816 NOS Chittur Project Dn - AE 4
07 Sep 2023 Work in progress | 63% Completed | 07/09/2023 Various dia of DI and HDPE pipes are supplied on site 74.324KM laid/out of 113km 1]. 90mmHDPE -58736m 2]. 110 mm HDPE -5079.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3087.20m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M FHTC 290/1816 NOS Chittur Project Dn - AE 4
17 Aug 2023 Work in progress | 63% Completed | 17/08/2023 Various dia of DI and HDPE pipes are supplied on site 73.092KM laid/out of 113km 1]. 90mmHDPE -57503.50m 2]. 110 mm HDPE -5079.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3087.20m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
04 Aug 2023 Work in progress | 63% Completed | 04/08/2023 Various dia of DI and HDPE pipes are supplied on site 73.092KM laid/out of 113km 1]. 90mmHDPE -57503.50m 2]. 110 mm HDPE -5079.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3087.20m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
19 Jul 2023 Work in progress | 63% Completed | 19/07/2023 Various dia of DI and HDPE pipes are supplied on site 72.223KM laid/out of 113km 1]. 90mmHDPE -56674.50 m 2]. 110 mm HDPE -5079.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3087.20m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4