Status Date Overall Project Status Project Officer Contact
06 Jul 2023 Work in progress | 62% Completed | 06/07/2023 Various dia of DI and HDPE pipes are supplied on site 71.088KM laid/out of 113km 1]. 90mmHDPE -55003 m 2]. 110 mm HDPE -5079.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3043.10m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
29 Jun 2023 Work in progress | 62% Completed | 29/06/2023 Various dia of DI and HDPE pipes are supplied on site 71.088KM laid/out of 113km 1]. 90mmHDPE -55003 m 2]. 110 mm HDPE -5079.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3043.10m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
23 Jun 2023 Work in progress | 57% Completed | 23/06/2023 Various dia of DI and HDPE pipes are supplied on site 66.930KM laid/out of 113km 1]. 90mmHDPE -52948 m 2]. 110 mm HDPE -4976.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3043.10m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
16 Jun 2023 Work in progress | 57% Completed | 16/06/2023 Various dia of DI and HDPE pipes are supplied on site 64.585KM laid/out of 113km 1]. 90mmHDPE -50725 m 2]. 110 mm HDPE -4854.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -3043.10m, 5]. 80 mm GI -833.70 M 6] . 100 mm GI -63.40 M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
09 Jun 2023 Work in progress | 55% Completed | 09/06/2023 Various dia of DI and HDPE pipes are supplied on site 63.008KM laid/out of 113km 1]. 90mmHDPE -48228m 2]. 110 mm HDPE -4716.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -2914.00m, 5]. 80 mm GI -779.62 M 6] . 100 mm GI -55.60M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
02 Jun 2023 Work in progress | 51% Completed | 02/06/2023 Various dia of DI and HDPE pipes are supplied on site 61.793KM laid/out of 113km 1]. 90mmHDPE -47013m 2]. 110 mm HDPE -4716.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -2914.00m, 5]. 80 mm GI -779.62 M 6] . 100 mm GI -55.60M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
26 May 2023 Work in progress | 51% Completed | 26/05/2023 Various dia of DI and HDPE pipes are supplied on site 59.823KM laid/out of 113km 1]. 90mmHDPE -45043 m 2]. 110 mm HDPE -4716.10m 3]. 160mm HDPE -1558m , 4]. 140mm pvc -2914.00m, 5]. 80 mm GI -779.62 M 6] . 100 mm GI -55.60M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6 Chittur Project Dn - AE 4
19 May 2023 Work in progress | 50% Completed | 19/05/2023 Various dia of DI and HDPE pipes are supplied on site 57.032KM laid/out of 113km 1]. 90mmHDPE -42612 m 2]. 110 mm HDPE -4716.10m 3]. 160mm HDPE -1198m , 4]. 140mm pvc -2914.00m, 5]. 80 mm GI -779.62 M 6] . 100 mm GI -55.60M 7}.700mmDI-1863.20M 8}.350mmDI-405.15m 9)200mm DI-6M Chittur Project Dn - AE 4
11 May 2023 Work in progress | 47% Completed | 11/05/2023 Various dia of DI and HDPE pipes are supplied on site 54.660KM laid/out of 113km 1]. 90mmHDPE -40347 m 2]. 110 mm HDPE -4716.10m 3]. 160mm HDPE -1198m , 4]. 140mm pvc -2914.00m, 5]. 80 mm GI -773.62 M 6] . 100 mm GI -55.60M 7}.700mmDI-1787.30M 8}.350mmDI-379.80m 9)200mm DI-6M Chittur Project Dn - AE 4
05 May 2023 Work in progress | 47% Completed | 05/05/2023 Various dia of DI and HDPE pipes are supplied on site 52.319KM laid/out of 113km 1]. 90mmHDPE -38219 m 2]. 110 mm HDPE -4716.10m 3]. 160mm HDPE -1144m , 4]. 140mm pvc -2803.00m, 5]. 80 mm GI -768.00 M 6] . 100 mm GI -55.60M 7}.700mmDI-1754.30M 8}.350mmDI-370.05m 9)200mm DI-6M Chittur Project Dn - AE 4