Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Apr 2023 Work in progress | 43% Completed | 28/04/2023 Various dia of DI and HDPE pipes are supplied on site 49.155KM laid/out of 113km 1]. 90mmHDPE -38057 m 2]. 110 mm HDPE -4249.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2803.00m, 5]. 80 mm GI -768.00 M 6] . 100 mm GI -55.60M 7}.700mmDI-1754.30M 8}.350mmDI-370.05m Chittur Project Dn - AE 4
21 Apr 2023 Work in progress | 41% Completed | 21/04/2023 Various dia of DI and HDPE pipes are supplied on site 47.862KM laid/out of 113km 1]. 90mmHDPE -37323m 2]. 110 mm HDPE -4249.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2803.00m, 5]. 80 mm GI -208.68M 6] . 100 mm GI -55.60M 7}.700mmDI-1754.30M 8}.350mmDI-370.05m Chittur Project Dn - AE 4
10 Apr 2023 Work in progress | 40% Completed | 10/04/2023 Various dia of DI and HDPE pipes are supplied on site 45.527KM laid/out of 113km 1]. 90mmHDPE -35878m 2]. 110 mm HDPE -3767.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2576.50m, 5]. 80 mm GI -208.68M 6] . 100 mm GI -55.60M 7}.700mmDI-1638.80M 8}.350mmDI-304.05m Chittur Project Dn - AE 4
31 Mar 2023 Work in progress | 36% Completed | 31/03/2023 Various dia of DI and HDPE pipes are supplied on site 40.7141KM laid/out of 113km 1]. 90mmHDPE -32257 m 2]. 110 mm HDPE -2874.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2560.00m, 5]. 80 mm GI -73.26M 6] . 100 mm GI -55.60M 7}.700mmDI-1491.90M 8}.350mmDI-304.05m Chittur Project Dn - AE 4
24 Mar 2023 Work in progress | 34% Completed | 24/03/2023 Various dia of DI and HDPE pipes are supplied on site 39.321KM laid/out of 113km 1]. 90mmHDPE -27943.50 2]. 110 mm HDPE -2572.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2225.00m, 5]. 80 mm GI -56.10M 6] . 100 mm GI -50M 7}.700mmDI-1264.90M 8}.350mmDI-304.05m Chittur Project Dn - AE 4
17 Mar 2023 Work in progress | 34% Completed | 17/03/2023 Various dia of DI and HDPE pipes are supplied on site 39.321KM laid/out of 113km 1]. 90mmHDPE -27943.50 2]. 110 mm HDPE -2572.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2225.00m, 5]. 80 mm GI -56.10M 6] . 100 mm GI -50M 7}.700mmDI-1264.90M 8}.350mmDI-304.05m Chittur Project Dn - AE 4
09 Mar 2023 Work in progress | 34% Completed | 09/03/2023 Various dia of DI and HDPE pipes are supplied on site 39.321KM laid/out of 113km 1]. 90mmHDPE -25212.50m 2]. 110 mm HDPE -2458.10m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2225.00m, 5]. 80 mm GI -56.10M 6] . 100 mm GI -50M 7}.700mmDI-926.40M 8}.350mmDI-304.05m Chittur Project Dn - AE 4
05 Mar 2023 Work in progress | 34% Completed | 05/03/2023 Various dia of DI and HDPE pipes are supplied on site 38.181 KM laid/out of 113km 1]. 90mmHDPE -24636m 2]. 110 mm HDPE -2109.10 m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2225.00m, 5]. 80 mm GI -56.10M 6] . 100 mm GI -50M 7}.700mmDI-711.90M 8}.350mmDI-304.05m Chittur Project Dn - AE 4
24 Feb 2023 Work in progress | 24% Completed | 24/02/2023 Various dia of DI and HDPE pipes are supplied on site 28.525 KM laid/out of 113km 1]. 90mmHDPE -23323m 2]. 110 mm HDPE -1391.10 m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2225.00m, 5]. 80 mm GI -56.10M 6] . 100 mm GI -50M 7}.700mmDI-196M 8}.350mmDI-194.90M Chittur Project Dn - AE 4
17 Feb 2023 Work in progress | 23% Completed | 17/02/2023 Various dia of DI and HDPE pipes are supplied on site 26.815 KM laid/out of 113km 1]. 90mmHDPE -22122m 2]. 110 mm HDPE -1272.10 m 3]. 160mm HDPE -1099 m , 4]. 140mm pvc -2225.00m, 5]. 80 mm GI -56.10M 6] . 100 mm GI -50M Chittur Project Dn - AE 4