Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Sep 2022 RCC for the Foundation work for WTP building, clear water sump and filter house is is completed on 29.08.22. Compound wall construction work at WTP location in progress. Foundation PCC for clari flocculator is completed. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
27 Aug 2022 RCC for the Foundation work for WTP building, clear water sump and filter house is is scheduled on 29.08.22s. Compound wall construction work at WTP location in progress. Also earth work for clari flocculator is completed. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
23 Aug 2022 Foundation work for WTP building, clear water sump and filter house is in progress. Compound wall construction work at WTP location in progress. Also earth work for clari flocculator is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
23 Aug 2022 Foundation work for WTP building, clear water sump and filter house is in progress. Compound wall construction work at WTP location in progress. Also earth work for clari flocculator is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
19 Aug 2022 Levelling course PCC for clear water sump and filter house is scheduled on 19.08.22. Compound wall construction work at WTP location in progress. Also earth work for clari flocculator is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
12 Aug 2022 Earth work excavation for filter house and clear water sump at wtp location completed. Compound wall construction work at WTP location in progress. Also earth work for clari flocculator is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
07 Aug 2022 Earth work excavation for filter house and clear water sump at wtp location is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
03 Aug 2022 Earth work excavation for filter house and clear water sump at wtp location is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
31 Jul 2022 Earth work excavation for filter house and clear water sump at wtp location is in progress. Pipe laying work of distribution pipe lines in progress. Payyannur UIDSSMT AE 3
26 Jul 2022 Earth work excavation for filter house and clear water sump at wtp location is in progress. Pipe laying work of distribution pipe lines started on 26.07.2022 Payyannur UIDSSMT AE 3