Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Nov 2022 Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in progress. Plastering work of Clear water sump at Kannadipoyyil is in progress. RCC of clear water sump wall and roof slab, Filter bed wall, Chemical room and chlorinator room roof slab, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
01 Nov 2022 Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building has started. Plastering work of Clear water sump at Kannadipoyyil in progress. RCC of clear water sump wall and roof slab, Filter bed wall, Chemical room and chlorinator room roof slab, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
28 Oct 2022 Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building has started. Plastering work of Clear water sump at Kannadipoyyil in progress. RCC of clear water sump wall and roof slab, Filter bed wall, Chemical room and chlorinator room roof slab, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
26 Oct 2022 Construction work of 4 MLD WTP is in progress. RCC of clear water sump wall, roof slab, Filter bed wall, Chemical room and chlorinator room roof slab, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80%completed. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
23 Oct 2022 Construction work of 4 MLD WTP is in progress. RCC of clear water sump wall, roof slab, Filter bed wall, Chemical room and chlorinator room roof slab, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80%completed. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
20 Oct 2022 Construction work of 4 MLD WTP is in progress. RCC of clear water sump wall, Filter bed wall, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80%completed. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
17 Oct 2022 Construction work of 4 MLD is in progress. RCC of clear water sump wall, Filter bed wall, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
15 Oct 2022 Construction work of 4MLD WTP is in progress. RCC of clear water sump wall, Filter bed wall, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
12 Oct 2022 Construction work of 4MLD WTP is in progress. RCC of clear water sump wall, Filter bed wall, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3
09 Oct 2022 RCC of clear water sump wall,Filter bed wall, Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed.Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress. Payyannur UIDSSMT AE 3