Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Dec 2022 1. Construction of Intake Well Cum Pumphouse at Thumbathadam : 8 m dia intake well construction work is in progress. RCC work of well steining is ongoing. 2. Raw Water and Clear water Pumping Mains and transmission mains: All the required pipes as per NIT is supplied by the contractor. Total 13 km pipe laid out of 21.20 km. 3. Construction of 4.00 MLD Water Treatment Plant at Kannadipoyil : 80% of the work is completed. Construction work of clarifier is ongoing. Finishing work of WTP building is in progress. Filter media work yet to be started. 4. Construction of 6.50 L.L capacity OHSR at Water Treatment Plant at Kannadipoyil for Zone-I : Work is in good progress. RCC work upto deck beam is completed. 5.Construction of 4.50 L.L capacity OHSR at Vellora and 0.50 L.L Break pressure tank at Perumbadavu for Zone-II : RCC of columns and brace beams of 4.5 LL OHSR is in progress. Construction work of 0.50LL BP tank at Perumbadavu yet to be started. 6. Supplying and Laying Distribution Network for Zone-I & Zone-II : All the required pipes as per NIT is supplied by the contractor. Total 110 km pipe laid out of 202 km. HTC work is also in progress. Total 627 HTC provided out of 6543. 7. Supply Erection of Raw water and Clear water pump sets at Intake Well, Booster and WTP Pump houses , Construction of 4.50m RCC weir at Thumbathadam etc not started. Payyannur UIDSSMT AE 3
28 Dec 2022 1. Construction of Intake Well Cum Pumphouse at Thumbathadam : 8 m dia intake well construction work is in progress. RCC work of well steining is ongoing. 2. Raw Water and Clear water Pumping Mains and transmission mains: All the required pipes as per NIT is supplied by the contractor. Total 13 km pipe laid out of 21.20 km. 3. Construction of 4.00 MLD Water Treatment Plant at Kannadipoyil : 80% of the work is completed. Construction work of clarifier is ongoing. Finishing work of WTP building is in progress. Filter media work yet to be started. 4. Construction of 6.50 L.L capacity OHSR at Water Treatment Plant at Kannadipoyil for Zone-I : Work is in good progress. RCC work upto deck beam is completed. 5.Construction of 4.50 L.L capacity OHSR at Vellora and 0.50 L.L Break pressure tank at Perumbadavu for Zone-II : RCC of columns and brace beams of 4.5 LL OHSR is in progress. Construction work of 0.50LL BP tank at Perumbadavu yet to be started. 6. Supplying and Laying Distribution Network for Zone-I & Zone-II : All the required pipes as per NIT is supplied by the contractor. Total 110 km pipe laid out of 202 km. HTC work is also in progress. Total 627 HTC provided out of 6543. 7. Supply Erection of Raw water and Clear water pump sets at Intake Well, Booster and WTP Pump houses , Construction of 4.50m RCC weir at Thumbathadam etc not started. Payyannur UIDSSMT AE 3
27 Dec 2022 Construction work of intake well cum pump house at Thumbathadam is in progress,. RCC of well curb has done. Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in final stage. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Construction work of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location is in good progress. Foundation concrete of Flash mixer and aerator , clarofloculator side wall bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress Payyannur UIDSSMT AE 3
24 Dec 2022 Construction work of intake well cum pump house at Thumbathadam is in progress,. RCC of well curb has done. Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in final stage. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Construction work of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location is in good progress. Foundation concrete of Flash mixer and aerator , clarofloculator side wall bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3
22 Dec 2022 Construction work of intake well cum pump house at Thumbathadam is in progress,. RCC of well curb has done. Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in final stage. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Construction work of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location is in good progress. Foundation concrete of Flash mixer and aerator , clarofloculator side wall bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3
19 Dec 2022 Construction work of intake well cum pump house at Thumbathadam is in progress,. RCC of well curb has done. Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in final stage. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Construction work of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location is in good progress. Foundation concrete of Flash mixer and aerator , clarofloculator side wall bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3
14 Dec 2022 Construction work of intake well cum pump house at Thumbathadam is in progress,. RCC of well curb has done. Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in final stage. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Construction work of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location is in good progress. Foundation concrete of Flash mixer and aerator , clarofloculator side wall bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3
12 Dec 2022 Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in progress. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3
08 Dec 2022 Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in progress. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3
05 Dec 2022 Construction work of 4 MLD WTP is in progress. Construction work of 1LL OH tank above wtp building is in progress. Plastering work of wtp building is in progress. Construction of clear water pump house at wtp is in progress. Construction work of clear water sump is almost finished. Column footing for the foundation of 4.5 LL OHSR at Vellora and 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator , clarofloculator bottom slab etc are completed. Compound wall construction work at WTP location is 80% completed. Pipe laying work of distribution pipe lines and pumping main in progress. HTC work is also in progress. Payyannur UIDSSMT AE 3