06 Oct 2022 RCC of clear water sump wall,Filter bed wall, Column footing for the foundation of 4.5 LL OHSR at Vellora, Column footing of 6.50LL OHSR at WTP location, Foundation concrete of Flash mixer and aerator is also completed, clarofloculator bottom slab etc are completed.Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
03 Oct 2022 RCC of clear water sump wall is in progress. Column footing for the foundation of 4.5 LL OHSR at Vellora is completed. RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
30 Sep 2022 RCC of clear water sump wall is in progress. Column footing for the foundation of 4.5 LL OHSR at Vellora is completed. RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
26 Sep 2022 Earth work excavation and PCC for the foundation of 4.5 LL OHSR at vellora is completed. RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
24 Sep 2022 Earth work excavation and PCC for the foundation of 4.5 LL OHSR at vellora is completed. RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
21 Sep 2022 Earth work excavation and PCC for the foundation of 4.5 LL OHSR at vellora is completed. RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
19 Sep 2022 Earth work excavation and PCC for the foundation of 4.5 LL OHSR at vellora is completed. RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
16 Sep 2022 RCC of Filter bed wall is completed. Column footing of 6.50LL OHSR at WTP location is completed. Foundation concrete of Flash mixer and aerator is also completed. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
12 Sep 2022 RCC floor slab of clarifloculator is completed. RCC of Filter bed wall is in progress. Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Pipe laying work of distribution pipe lines and pumping main in progress Payyannur UIDSSMT AE 3
09 Sep 2022 RCC floor slab of clarifloculator is completed. RCC of Filter bed wall is in progress. for the Foundation work for WTP building, clear water sump completed . Compound wall construction work at WTP location in progress. Foundation PCC for clari flocculator is completed. Pipe laying work of distribution pipe lines in progress Payyannur UIDSSMT AE 3