Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Feb 2021 | progress | Malapuram Proj Dn AE 4 | |
12 Feb 2021 | progress | Malapuram Proj Dn AE 4 | |
06 Feb 2021 | work in progress 4.5 km laid | Malapuram Proj Dn AE 4 | |
30 Jan 2021 | laying pipe line progressing 3.0Km complete | Malapuram Proj Dn AE 4 | |
26 Jan 2021 | MOU place with PWD for the road which are not in DLP and started laying work | Malapuram Proj Dn AE 4 | |
24 Dec 2020 | All pipes and specials supplied at site and work commenced after placing Mou with PWD on 23/12/20 | Malapuram Proj Dn AE 4 | |
17 Nov 2020 | SUPPLY ORDER PLACED FOR PIPES BY CONTRACTOR AND EXPECTING TO COMMENCE THE WORK BY DECEMBER 1ST WEEK | Malapuram Proj Dn AE 4 | |
01 Nov 2020 | WORK ORDER ISSUED & AGMT EXECUTED | Malapuram Proj Dn AE 4 | |
11 Oct 2020 | awaiting approval of Tender | Malapuram Proj Dn AE 4 | |
03 Sep 2020 | tender process | Malapuram Proj Dn AE 4 |