Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 May 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 80 percentage of distribution pipe work also completed, 80 percentage of road reformation work is also completed with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
16 Mar 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 80 percentage of distribution pipe work also completed, 80 percentage of road reformation work is also completed with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
02 Feb 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
01 Feb 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
27 Jan 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
19 Jan 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
18 Jan 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
13 Jan 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
12 Jan 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
11 Jan 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also comleted with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4