01 Jan 2022 600 mm DI pipe line work completed, road restoration work in progress Malapuram Proj Dn AE 4
30 Nov 2021 600 mm DI work in progress 63 percentage of work completed Malapuram Proj Dn AE 4
22 Nov 2021 600 mm DI work in progress 63 percentage of work completed Malapuram Proj Dn AE 4
19 Nov 2021 600 mm DI work in progress 63 percentage of work completed Malapuram Proj Dn AE 4
18 Nov 2021 600 mm DI work in progress 63 percentage of work completed Malapuram Proj Dn AE 4
04 Oct 2021 Continuous rain obstructed pipe line work in Pwd roads.. Malapuram Proj Dn AE 4
25 Sep 2021 Pwd permission is expect to give soon after BG.. Malapuram Proj Dn AE 4
04 Sep 2021 Waiting for PWD permission after Monsoon season Malapuram Proj Dn AE 4
24 Aug 2021 20km pipe layin completed...BG remitted to PWD..road sanction expect this month Malapuram Proj Dn AE 4
09 Jul 2021 BG amount reported to HO ..for getting permission in DLP roads ..19Km pipe laying completed.MS work near Tank progress Malapuram Proj Dn AE 4