Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jan 2022 | 600 mm DI pipe line work completed, road restoration work in progress | Malapuram Proj Dn AE 4 | |
30 Nov 2021 | 600 mm DI work in progress 63 percentage of work completed | Malapuram Proj Dn AE 4 | |
22 Nov 2021 | 600 mm DI work in progress 63 percentage of work completed | Malapuram Proj Dn AE 4 | |
19 Nov 2021 | 600 mm DI work in progress 63 percentage of work completed | Malapuram Proj Dn AE 4 | |
18 Nov 2021 | 600 mm DI work in progress 63 percentage of work completed | Malapuram Proj Dn AE 4 | |
04 Oct 2021 | Continuous rain obstructed pipe line work in Pwd roads.. | Malapuram Proj Dn AE 4 | |
25 Sep 2021 | Pwd permission is expect to give soon after BG.. | Malapuram Proj Dn AE 4 | |
04 Sep 2021 | Waiting for PWD permission after Monsoon season | Malapuram Proj Dn AE 4 | |
24 Aug 2021 | 20km pipe layin completed...BG remitted to PWD..road sanction expect this month | Malapuram Proj Dn AE 4 | |
09 Jul 2021 | BG amount reported to HO ..for getting permission in DLP roads ..19Km pipe laying completed.MS work near Tank progress | Malapuram Proj Dn AE 4 |