Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Jun 2021 18km pipe laying completed MS work progressing.. Malapuram Proj Dn AE 4
01 Jun 2021 4.5km road cutting permission not obtained due to DLP and non getting fund for BG Malapuram Proj Dn AE 4
01 Jun 2021 Progress slow due to lock down issues Malapuram Proj Dn AE 4
18 May 2021 Progress heldup due to lock down Malapuram Proj Dn AE 4
12 May 2021 About 8.5 km pipe Replacement completed.work could only done at night due to heavy city traffic. Malapuram Proj Dn AE 4
22 Apr 2021 4.5km road cutting permission from PWD not obtained due to DLP. PWD Requested to place BG in DLP roads. KIIFB not yet passed to place BG. hence work couldn't start these part Malapuram Proj Dn AE 4
21 Apr 2021 7.3Km pipe replacing completed out of 33km . inter connection works and pipe laying progressing. Work could only be started at Night duet heavy traffic in cities during day times Malapuram Proj Dn AE 4
15 Apr 2021 7.0km pipe replacing laying completed. Inter connection to old main line is progressing Malapuram Proj Dn AE 4
16 Mar 2021 Out of 33.5Km pipe laying 6.20Km Completed . 22Km pipes ( all DI & MS)supplied 12Km PVC pipes balance to supply. Work could only be done at Night due to heavy City traffic ,hence the progress is slow as progress expected . Malapuram Proj Dn AE 4
15 Mar 2021 work progressing in PWD roads Malapuram Proj Dn AE 4