Status Date Overall Project Status Project Officer Contact
03 Apr 2023 Pipe line work completed for 24Km and balance pending for non getting permission from PWD. Road restoration work for the completed portion BM completed Balance BC work is completed. Malapuram Proj Dn AE 4
14 Feb 2023 Pipe line work completed for 24Km and balance pending for non getting permission from PWD. Road restoration work for the completed portion BM completed Balance BC work is on going Malapuram Proj Dn AE 4
15 Dec 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 83 percentage of work completed Malapuram Proj Dn AE 4
15 Oct 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 83 percentage of work completed Malapuram Proj Dn AE 4
19 Aug 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 81 percentage of work completed Malapuram Proj Dn AE 4
11 Jul 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 81 percentage of work completed. Malapuram Proj Dn AE 4
13 Jun 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 81 percentage of work completed. Malapuram Proj Dn AE 4
13 Jun 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
11 Jun 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 75 percentage of distribution pipe work also completed, 80 percentage of road reformation work also completed with the supervision of PWD officials. overall 73 percentage of work completed. Malapuram Proj Dn AE 4
11 May 2022 600 mm DI k9 pipe laying work completed. all replacing damaged AC pipe work are completed and about 80 percentage of distribution pipe work also completed, 80 percentage of road reformation work is also completed with the supervision of PWD officials. overall 79 percentage of work completed. Malapuram Proj Dn AE 4