Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Feb 2024 | 29500m laying completed,1502onnections completed, 14th and part bill submitted.Concreting work on progress.Tubewell work completed at chirayilkulam | Chavara AE | |
18 Feb 2024 | 29500m laying completed, 1496 connections completed, 14th and part bill submitted.Concreting work on progress.Tubewell work on progress | Chavara AE | |
14 Feb 2024 | 29500m laying completed, 1486 connections completed, 14th and part bill submitted.Concreting work on progress.Tubewell work on progress | Chavara AE | |
12 Feb 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work on progress.Tubewell work on progress | Chavara AE | |
07 Feb 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work on progress.Tubewell work on progress | Chavara AE | |
03 Feb 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work on progress | Chavara AE | |
30 Jan 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work on progress | Chavara AE | |
26 Jan 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work ongoing | Chavara AE | |
22 Jan 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work ongoing | Chavara AE | |
18 Jan 2024 | 29500m laying completed, 1476 connections completed, 14th and part bill submitted.Concreting work ongoing | Chavara AE |