Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Sep 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
27 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
23 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification and Interconnection work in progress... | Kollam Project HD | |
22 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
21 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... Interconnection progress at ward 11 | Kollam Project HD | |
19 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
18 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
17 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
16 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection completed at ward 19 | Kollam Project HD | |
15 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection completed at ward 19 | Kollam Project HD |