Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection completed at ward 19 | Kollam Project HD | |
12 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection progress... | Kollam Project HD | |
11 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection progress... | Kollam Project HD | |
10 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectification progress... | Kollam Project HD | |
09 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work and leak rectification work in progress.. | Kollam Project HD | |
08 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work and leak rectification work in progress.. | Kollam Project HD | |
07 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work in progress... | Kollam Project HD | |
05 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work in progress... | Kollam Project HD | |
04 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos.Road restoration work in progress... | Kollam Project HD | |
03 Aug 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos.Road section work progress for restoration ... | Kollam Project HD |