Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection completed at ward 19 Kollam Project HD
12 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection progress... Kollam Project HD
11 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectified and interconnection progress... Kollam Project HD
10 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 leak rectification progress... Kollam Project HD
09 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work and leak rectification work in progress.. Kollam Project HD
08 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work and leak rectification work in progress.. Kollam Project HD
07 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work in progress... Kollam Project HD
05 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos GI work in progress... Kollam Project HD
04 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos.Road restoration work in progress... Kollam Project HD
03 Aug 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos.Road section work progress for restoration ... Kollam Project HD