Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Sep 2022 | 1982 FHTC has been affected. Re - concreting work on progress. | Sasthamcotta WS Sn 1 - AE | |
07 Sep 2022 | 1982 FHTC has been affected. Re - concreting work on progress. | Sasthamcotta WS Sn 1 - AE | |
01 Sep 2022 | 1982 FHTC has been affected. Re - concreting work on progress. | Sasthamcotta WS Sn 1 - AE | |
28 Aug 2022 | 1962 FHTC has been affected including 60nos arranged by quotation. Pipeline extension work on progress. | Sasthamcotta WS Sn 1 - AE | |
26 Aug 2022 | 1962 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress. | Sasthamcotta WS Sn 1 - AE | |
21 Aug 2022 | 1915 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress. | Sasthamcotta WS Sn 1 - AE | |
19 Aug 2022 | 1915 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress | Sasthamcotta WS Sn 1 - AE | |
16 Aug 2022 | 1915 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress | Sasthamcotta WS Sn 1 - AE | |
12 Aug 2022 | 1915 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress | Sasthamcotta WS Sn 1 - AE | |
10 Aug 2022 | 1915 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress | Sasthamcotta WS Sn 1 - AE |