Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath.
Project |
Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath. |
Project Code |
KLMJJM08206538 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC(2643nos), PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath. |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
144252000
|
AS Number |
541/2020/WRD Dated 21/8/2020 |
TS Amount (Rs) |
61990000 |
TS Number |
ORDER No. TS/2020-2021/2020/16515 |
Total Bill Submitted (Rs) |
35536625 |
Total Bill Paid (Rs) |
335536625 |
Population Benefitted |
1488 |
Capacity in MLD |
2.14 |
Actual Project Completion Date |
13 Jun 2023 |
Coverage |
All wards of Sooranadu South Grama Panchayath. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission Phase I- 2020-21- RWSS to Sooranadu South- Providing FHTC, PVC pipe lineJ extension, supply and errection of pump sets, installation of bulk water meter etc. in Sooranadu South grama panchayath. |
Sasthamcottah WS Sn1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded. |
Sasthamcotta WS Sn 1 - AE |
|
25 Jun 2024 |
The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded. |
Sasthamcotta WS Sn 1 - AE |
|
24 Jun 2024 |
Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. |
Sasthamcotta WS Sn 1 - AE |
|
20 Jun 2024 |
Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. |
Sasthamcotta WS Sn 1 - AE |
|
12 Jun 2024 |
Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. |
Sasthamcotta WS Sn 1 - AE |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
01 Nov 2022 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission not obtained at Bharanikavu nalumukku |
No comments available. |
Pending |
01 Jul 2022 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission not obtained for KCT Jn puthanpura Mukku |
No comments available. |
Pending |
01 Jul 2022 |
Pending |
Pending |
Road Cut Related Risk |
Road cutting permission not obtained at pathram Malumel kadavu |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
22/01/2021 |
Scheduled date of Completion of the Project |
21 Dec 2021 |
Expected date of Completion |
14/01/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
04 Sep 2020 |