Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jun 2024 The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded. Sasthamcotta WS Sn 1 - AE
26 Jun 2024 The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded. Sasthamcotta WS Sn 1 - AE
25 Jun 2024 The work has delayed due to the delay in getting PWD/KRFB road cutting permission and RE sanction. The RE sanction now obatained on 25.04.2024. After getting the RE sanction the ime extension request was submitted by the contracor on 09.05.2024 and recommendation has been already forwarded. Sasthamcotta WS Sn 1 - AE
24 Jun 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
20 Jun 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
12 Jun 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
10 Jun 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
05 Jun 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
01 Jun 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
28 May 2024 Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE