Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Mar 2022 1534 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
23 Mar 2022 1534 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
21 Mar 2022 1534 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
17 Mar 2022 1534 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
14 Mar 2022 1443 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
10 Mar 2022 1443 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
10 Mar 2022 1437 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
08 Mar 2022 1437 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
06 Mar 2022 1427 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE
03 Mar 2022 1427 FHTC has been affected including 60nos arranged by quotation. pipeline extension work on progress Sasthamcotta WS Sn 1 - AE