Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Nov 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Revised Estimate submitted to Higher Authority for approval. | Sasthamcotta WS Sn 1 - AE | |
10 Nov 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress | Sasthamcotta WS Sn 1 - AE | |
24 Oct 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress | Sasthamcotta WS Sn 1 - AE | |
12 Oct 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress | Sasthamcotta WS Sn 1 - AE | |
09 Oct 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE | |
04 Oct 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE | |
27 Sep 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE | |
21 Sep 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE | |
18 Sep 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE | |
17 Sep 2022 | 2032 FHTC has been affected(Including 60 nos arranged by quotation.). Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE |