15 Feb 2024 out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
14 Feb 2024 Work temporarly closed waiting for RE sanction. Total 2215 FHTC has been affected. (Including 60 nos arranged by quotation). Sasthamcotta WS Sn 1 - AE
11 Feb 2024 Work temporarly closed waiting for RE sanction. Total 2215 FHTC has been affected. (Including 60 nos arranged by quotation). Sasthamcotta WS Sn 1 - AE
08 Feb 2024 Work temporarly closed waiting for RE sanction. Total 2215 FHTC has been affected. (Including 60 nos arranged by quotation). Sasthamcotta WS Sn 1 - AE
31 Jan 2024 Revised Estimate submitted to Higher Authority for approval.Waiting for RE sanction.Since work temporarly stopped. Total 2215 FHTC has been affected( Including 60 nos arranged by quotation. Sasthamcotta WS Sn 1 - AE
27 Jan 2024 Revised Estimate submitted to Higher Authority for approval.Waiting for RE sanction.Since work temporarly stopped. Total 2215 FHTC has been affected( Including 60 nos arranged by quotation. Sasthamcotta WS Sn 1 - AE
22 Jan 2024 Total 2215 FHTC has been affected( Including 60 nos arranged by quotation.Revised Estimate submitted to Higher Authority for approval.Waiting for RE sanction.Since work temporarly stopped. Sasthamcotta WS Sn 1 - AE
20 Jan 2024 Total 2215 FHTC has been affected( Including 60 nos arranged by quotation.Revised Estimate submitted to Higher Authority for approval.Waiting for RE sanction.Since work temporarly stopped. Sasthamcotta WS Sn 1 - AE
16 Jan 2024 Work temporarly closed waiting for RE sanction Sasthamcotta WS Sn 1 - AE
11 Jan 2024 Work temporarly closed waiting for RE sanction Sasthamcotta WS Sn 1 - AE