Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 May 2024 Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
20 May 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
16 May 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
14 May 2024 Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
07 May 2024 Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
06 May 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
04 May 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
02 May 2024 Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction.Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Sasthamcotta WS Sn 1 - AE
29 Apr 2024 Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE
27 Apr 2024 Out of 2463 connections 2215 FHTC's are Completed. ( including 60 nos arranged by quotation) Out of 25.9 km pipe laying 18.1 km completed. Work temporarly stopped due to getting Road Cuting Permission of Patharam Malumel road, Bharanikavu Nalumukku Road, KCT Jn Puthanpuramukku road from KRFB. Demand notice recieved from KRFB and Submitted to head office for fund request, Also waiting for RE sanction. Sasthamcotta WS Sn 1 - AE