Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Dec 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
02 Dec 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
01 Dec 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
30 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
29 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
28 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
27 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
25 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
24 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
23 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE |