Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing Kunnamkulam PH Sn - AE
25 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing Kunnamkulam PH Sn - AE
21 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed. Kunnamkulam PH Sn - AE
20 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed. Thrissur PH Dn EE
19 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed. Kunnamkulam PH Sn - AE
18 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed. Thrissur PH Dn EE
17 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed Thrissur PH Dn EE
16 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed Thrissur PH Dn EE
13 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed Kunnamkulam PH Sn - AE
12 Oct 2023 PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. PKG 2,3 Work order issued and agreement executed Kunnamkulam PH Sn - AE