Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
09 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Thrissur PH Dn EE | |
07 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Thrissur PH Dn EE | |
06 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Thrissur PH Dn EE | |
04 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Thrissur PH Dn EE | |
04 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
03 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Thrissur PH Dn EE | |
02 Nov 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing | Thrissur PH Dn EE | |
31 Oct 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing | Thrissur PH Dn EE | |
27 Oct 2023 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 95 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing | Thrissur PH Dn EE |