06 Apr 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1304 & house connection 1371 nos , Geo tagged -1326 nos completed. Palakkad Proj AE 3
04 Apr 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1294 & house connection 1371 nos , Geo tagged -1326 nos completed. Palakkad Proj AE 3
04 Apr 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1294 & house connection 1371 nos , Geo tagged -1326 nos completed. Palakkad Proj AE 3
03 Apr 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1294 & house connection 1371 nos , Geo tagged -1326 nos completed. Palakkad Proj AE 3
02 Apr 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1294 & house connection 1369 nos , Geo tagged -1324 nos completed. Palakkad Proj AE 3
01 Apr 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1294 & house connection 1366 nos , Geo tagged -1321 nos completed. Palakkad Proj AE 3
30 Mar 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1294 & house connection 1364 nos , Geo tagged -1317 nos completed. Palakkad Proj AE 3
27 Mar 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1290 & house connection 1359 nos , Geo tagged -1311 nos completed. Palakkad Proj AE 3
26 Mar 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1290 & house connection 1359 nos , Geo tagged -1311 nos completed. Palakkad Proj AE 3
25 Mar 2024 House connections and geo tagging is going.49.17/65.2 km completed. , GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1290 & house connection 1358 nos , Geo tagged -1311 nos completed. Palakkad Proj AE 3