Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Mar 2024 | 49.17/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1253 & HTC - 78/2623 completed | Palakkad Project Dn AE | |
24 Feb 2024 | 49.17/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1253 & HTC - 78/2623 completed | Palakkad Proj AE 3 | |
23 Feb 2024 | 49.17/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1253 & HTC - 74/2623 completed | Palakkad Proj AE 3 | |
21 Feb 2024 | 49.17/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1253 & HTC - 74/2623 completed | Palakkad Proj AE 3 | |
19 Feb 2024 | 49.17/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1247 & HTC - 73/2623 completed | Palakkad Proj AE 3 | |
16 Feb 2024 | 49.17/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1247 & HTC - 68/2623 completed | Palakkad Proj AE 3 | |
14 Feb 2024 | 47.6/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1224 & HTC - 65/2623 completed | Palakkad Project Dn AE | |
12 Feb 2024 | 47.5/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1224 & HTC - 65/2623 completed | Palakkad Project Dn EE | |
09 Feb 2024 | 46/65.2 km completed. remaining HDPE & GI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1224 & HTC - 50/2623 completed | Palakkad Project Dn EE | |
07 Feb 2024 | 44.03/65.2 km completed. remaining HDPE & DI pipe laying work on going, GI 5.135/5.826 km completed, All PWD road work completed. FHTC- 1212 & HTC - 35/2623 completed | Palakkad Proj Dn AE 4 |