Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
24 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
17 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
15 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
13 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
08 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
03 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
30 Aug 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
23 Aug 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
17 Aug 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE |