Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 May 2022 | Line extension work is going on. 75mm pvc pipe 840m, 90mm pvc pipe 540m and 110mm pvc pipe 460 m laying completed. | Alappuzha PH Sub Dn AEE | |
04 Feb 2022 | Line extension work is going on. 75mm pvc pipe 840m, 90mm pvc pipe 540m and 110mm pvc pipe 460 m laying completed | Alappuzha PH Sn AE | |
03 Feb 2022 | Line extension work is going on. 75mm pvc pipe 840m, 90mm pvc pipe 540m and 110mm pvc pipe 460 m laying completed | Alappuzha PH Sn AE | |
01 Feb 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
26 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
25 Jan 2022 | Line extension work is going on. 75mm pvc pipe 650m, 90mm pvc pipe 245m and 110mm pvc pipe 460 m laying completed | Alappuzha PH Sn AE | |
20 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
13 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
04 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
28 Dec 2021 | Line extension work is going on. 1970/1970 nos FTC completed | Alappuzha PH Sn AE |