Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Nov 2021 | Pipe line extension work is going on | Alappuzha PH Sn AE | |
04 Nov 2021 | Pipe line extension work started on 2/11/2021 | Alappuzha PH Sn AE | |
01 Nov 2021 | 1924/1970 nos FHTC completed. Due to rain pipe laying work not started. | Alappuzha PH Sn AE | |
28 Oct 2021 | 1924/1970 nos FHTC completed. Due to rain pipe laying work not started. | Alappuzha PH Sn AE | |
23 Oct 2021 | 1924/1970 nos FHTC completed. Due to rain pipe laying work not started. | Alappuzha PH Sn AE | |
18 Oct 2021 | 1924/1970 nos FHTC completed. Due to rain pipe laying work not started. | Alappuzha PH Sn AE | |
12 Oct 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
07 Oct 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
04 Oct 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE | |
30 Sep 2021 | 1924/1970 nos FHTC completed | Alappuzha PH Sn AE |