Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Dec 2022 | Awaiting for PWD road cutting sanction | Alappuzha PH Sn AE | |
22 Nov 2022 | Awaiting for PWD road cutting sanction | Alappuzha PH Sn AE | |
11 Nov 2022 | Awaiting for PWD Road cutting sanction | Alappuzha PH Sub Dn AEE | |
19 Aug 2022 | PWD Road Cutting Permission awaiting | Alappuzha PH Sn AE | |
08 Jul 2022 | Joint inspection progressing with road authority | Alappuzha PH Sub Dn AEE | |
06 Jul 2022 | Joint inspection progressing with road authority | Alappuzha PH Sub Dn AEE | |
24 Jun 2022 | Joint inspection progressing with road authority | Alappuzha PH Sub Dn AEE | |
17 Jun 2022 | Joint inspection progressing with road authority | Alappuzha PH Sn AE | |
04 Jun 2022 | Line extension work is going on. 75mm pvc pipe 840m, 90mm pvc pipe 540m and 110mm pvc pipe 460 m laying completed | Alappuzha PH Sub Dn AEE | |
28 May 2022 | Line extension work is going on. 75mm pvc pipe 840m, 90mm pvc pipe 540m and 110mm pvc pipe 460 m laying completed | Alappuzha PH Sub Dn AEE |