Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Feb 2021 | 1000/1970 house connection given | Kochi PH Dn EE | |
16 Feb 2021 | 872/1970 house connection given | Alappuzha PH Dn EE | |
06 Feb 2021 | 804/1970 house connections given | Alappuzha PH Dn EE | |
05 Feb 2021 | 780/1970 house connection given | Alappuzha PH Dn EE | |
15 Jan 2021 | 623/1970 house connections given | Alappuzha PH Dn EE | |
26 Dec 2020 | 394/1970 house connections given | Alappuzha PH Dn EE | |
19 Dec 2020 | 272/1970 fhtc connections given | Alappuzha PH Dn EE | |
12 Dec 2020 | 167 fhtc connections given out of 1970 connection target | Alappuzha PH Dn EE | |
05 Dec 2020 | 117 fhtc connections given out of 1970 connection target | Alappuzha PH Dn EE | |
05 Dec 2020 | Work in progress, 5.93% completed. | Alappuzha PH Dn EE |