Status Date Overall Project Status Project Officer Contact
16 Mar 2021 Work started.2 nos FHTC given Kollam Project Dn AE4
15 Mar 2021 Work started.2 nos FHTC given Kollam Project Dn AE4
07 Feb 2021 Selection Notice Issued on 18/12/2020 Kollam Project Dn AE4
02 Feb 2021 Selection Notice Issued on 18/12/2020 Kollam Project HD
11 Jan 2021 Selection Notice Issued on 18/12/2020. Agreement Not executed. Kollam Project Dn AE4
11 Jan 2021 Selection Notice Issued on 18/12/2020 Kollam Project Dn AE4
10 Dec 2020 Prequalification approval is obtained from CE'S office and Technical bid has opened on 09/12/2020 Kollam Project Dn AE4
28 Nov 2020 Prequalification submitted on 16/11/2020 to CE'S office Kollam Project HD
12 Sep 2020 WORK TENDERED Kollam Project Dn AE4