| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Jan 2022 | 1410 FHTC completed and is in progress | Kottarakkara PH Dn EE | |
| 24 Jan 2022 | 1387 FHTC effected | Kottarakkara PH Dn EE | |
| 21 Jan 2022 | 1387 FHTC effected | Kottarakkara PH Dn EE | |
| 18 Jan 2022 | 1345 FHTC effected | Kottarakkara PH Dn EE | |
| 08 Jan 2022 | 1344 FHTC effected | Kottarakkara PH Dn EE | |
| 04 Jan 2022 | work in progress | Kottarakkara PH Dn EE | |
| 31 Dec 2021 | 1324 nos FHTC COMPLETED | Kottarakkara PH Dn EE | |
| 27 Dec 2021 | 1277 nos FHTC COMPLETED | Kottarakkara PH Dn EE | |
| 22 Dec 2021 | 1277 nos FHTC COMPLETED | Kottarakkara PH Dn EE | |
| 19 Dec 2021 | 1266 nos FHTC completed | Kottarakkara PH Dn EE |