| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Jul 2021 | 364 FHTC given | Kollam Project Dn AE4 | |
| 01 Jul 2021 | 335 FHTC given | Kollam Project Dn AE4 | |
| 29 Jun 2021 | 325 FHTC given | Kollam Project Dn AE4 | |
| 24 Jun 2021 | 325 FHTC GIVEN | Kollam Project Dn AE4 | |
| 22 Jun 2021 | 310 nos. FHTC given | Kollam Project Dn AE4 | |
| 16 Jun 2021 | 275 nos FHTC given | Kollam Project Dn AE4 | |
| 14 Jun 2021 | Work restarted ,262 nos FHTC given | Kollam Project Dn AE4 | |
| 10 Jun 2021 | Contractor informed that they will stop the FHTC work in Ummannoor panchayath from 5.6.2021 to 9.6.2021 based on the instruction of Sector Magistrate -COVID -19 | Kollam Project Dn AE4 | |
| 09 Jun 2021 | Contractor informed that they will stop the FHTC work in Ummannoor panchayath from 5.6.2021 to 9.6.2021 based on the instruction of Sector Magistrate -COVID -19 | Kollam Project Dn AE4 | |
| 08 Jun 2021 | Contractor informed that they will stop the FHTC work in Ummannoor panchayath from 5.6.2021 to 9.6.2021 based on the instruction of Sector Magistrate -COVID -19 | Kollam Project Dn AE4 |