| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Jul 2026 | 64.90km laying ,4118nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 07 Jul 2026 | 64.90km laying ,4102nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 17 Jun 2026 | 64.90km laying ,3908nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 02 Jun 2026 | 64.90km laying ,3908nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 13 Apr 2026 | 64.90km laying ,3908nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 25 Mar 2026 | 64.90km laying ,3895nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 17 Mar 2026 | 60km laying ,3830nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 07 Mar 2026 | 60km laying ,3830nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 27 Feb 2026 | 60km laying ,3830nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 21 Feb 2026 | 60km laying ,3803nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE |