| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 May 2025 | 58.26km laying ,3550nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 03 May 2025 | 58.26km laying ,3488nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 28 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 22 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 16 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 09 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 03 Apr 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 27 Mar 2025 | 58.26km laying ,3476nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 20 Mar 2025 | 58.26km laying ,3469nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 11 Mar 2025 | 58.26km laying ,3469nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE |