Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Sep 2025 58.26km laying ,3727nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
30 Aug 2025 58.26km laying ,3719nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
23 Aug 2025 58.26km laying ,3712nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
18 Aug 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
13 Aug 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
13 Aug 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
05 Aug 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
28 Jul 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
19 Jul 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE
15 Jul 2025 58.26km laying ,3689nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed Perlassery Sn 2 AE