| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Nov 2025 | 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 12 Nov 2025 | 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 05 Nov 2025 | 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 29 Oct 2025 | 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 25 Oct 2025 | 58.26km laying ,3759nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 16 Oct 2025 | 58.26km laying ,3745nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 13 Oct 2025 | 58.26km laying ,3745nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 09 Oct 2025 | 58.26km laying ,3745nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 03 Oct 2025 | 58.26km laying ,3731nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE | |
| 25 Sep 2025 | 58.26km laying ,3731nos.FHTC provided and Pachikkad tank work completed . Valiyakund Colony pipe line work completed | Perlassery Sn 2 AE |