Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Feb 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
31 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
30 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
29 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
28 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
27 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
26 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
25 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tender submitted to Govt for approval on 06-01-2025. Kollam Project HD
24 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 84.3% (27 numbers supplied & installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tendered-Negotiated amount of Tide projects Rs 18531500/- 48.02/ above TPAC submitted to CE on 13.12.24. Kollam Project HD
23 Jan 2025 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 84.3% (27 numbers supplied & installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Tendered-Negotiated amount of Tide projects Rs 18531500/- 48.02/ above TPAC submitted to CE on 13.12.24. Kollam Project HD