| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Mar 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 93%(30 numbers supplied at site & 29 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 06-01-2025 | Kollam Project HD | |
| 11 Mar 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 93%(30 numbers supplied at site & 29 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 06-01-2025 | Kollam Project HD | |
| 10 Mar 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 93%(30 numbers supplied at site & 29 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 06-01-2025 | Kollam Project HD | |
| 18 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 16-01-2025 | Kollam Project HD | |
| 17 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 16-01-2025 | Kollam Project HD | |
| 15 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 16-01-2025 | Kollam Project HD | |
| 14 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 16-01-2025 | Kollam Project HD | |
| 13 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 16-01-2025 | Kollam Project HD | |
| 12 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to tender sanction to Government (48.02%) on 16-01-2025 | Kollam Project HD | |
| 03 Feb 2025 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 87.5% (28 numbers supplied at site & 27 installed) Electrical Works 95% (Finishing work in progress)...50 KLD FSTP.-Submitted to Govt on 06-01-2025 for approval and tender sanction . | Kollam Project HD |