Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jan 2022 Road restoration in panchayath roads completed Kattappana Project Dn EE
20 Sep 2021 out of 2650m pipe line replacement, 340m of pipe line in PWD road is left. The Gravity main replaced is connected to this portion of existing AC line and charged . The line is fuctioning effectivly. Along the alignment there is UG power cable passing which is the dedicated power line to our JICA Scheme. Also the PWD road is under DLP Kattappana Project Dn EE
11 Jul 2021 Application for extension of time of completion submitted to SEs office Kattappana Project Dn EE
14 May 2021 Tile work,road work in progress Kattappana Project Dn EE
18 Mar 2021 Road restoration work in progress Kattappana Project Dn EE
25 Jan 2021 Pipe Laying for 1100m completed out of 2650m Kattappana Project Dn EE
22 Nov 2020 Work started on 20/11/2020 Kattappana Project Dn EE
11 Nov 2020 The factory inspection of pipes completed.Pipes in transit Kattappana Project Dn EE
01 Jul 2020 Pending as the pipe supply is delayed due to COVID Emergencies Kattappana Project Dn EE
24 Jun 2020 Agreement executed Kattappana Project Dn EE