Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Jan 2022 | Road restoration in panchayath roads completed | Kattappana Project Dn EE | |
20 Sep 2021 | out of 2650m pipe line replacement, 340m of pipe line in PWD road is left. The Gravity main replaced is connected to this portion of existing AC line and charged . The line is fuctioning effectivly. Along the alignment there is UG power cable passing which is the dedicated power line to our JICA Scheme. Also the PWD road is under DLP | Kattappana Project Dn EE | |
11 Jul 2021 | Application for extension of time of completion submitted to SEs office | Kattappana Project Dn EE | |
14 May 2021 | Tile work,road work in progress | Kattappana Project Dn EE | |
18 Mar 2021 | Road restoration work in progress | Kattappana Project Dn EE | |
25 Jan 2021 | Pipe Laying for 1100m completed out of 2650m | Kattappana Project Dn EE | |
22 Nov 2020 | Work started on 20/11/2020 | Kattappana Project Dn EE | |
11 Nov 2020 | The factory inspection of pipes completed.Pipes in transit | Kattappana Project Dn EE | |
01 Jul 2020 | Pending as the pipe supply is delayed due to COVID Emergencies | Kattappana Project Dn EE | |
24 Jun 2020 | Agreement executed | Kattappana Project Dn EE |