Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Jun 2023 PWD Tarring work pending Piravom Project Dn AE 1
08 Jun 2023 PWD Tarring work pending Piravom Project Dn AE 1
05 Jun 2023 PWD Tarring work pending Piravom Project Dn AE 1
29 May 2023 Pipe laying through PWD road is completed. Due to heavy summer rain road restoration work cannot be completed. Piravom Project Dn AE 1
16 Aug 2022 Pipe laying through PWD road is completed. Due to heavy summer rain road restoration work cannot be completed. Kattappana Project Dn EE
15 Aug 2022 Pipe laying through PWD road is completed. Due to heavy summer rain road restoration work cannot be completed. Kattappana Project Dn EE
11 Jul 2022 Road restoration work through main road to be completed afteer monsoon Kattappana Project Dn EE
28 May 2022 Pipe laying through PWD road also completed Kattappana Project Dn EE
16 Apr 2022 Pipe laying through Pandyanpara Maneed PWD road in progress Kattappana Project Dn EE
17 Mar 2022 NOC for road cutting from PWD roads obtained on 16.03.2022 Kattappana Project Dn EE