Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Jun 2023 | PWD Tarring work pending | Piravom Project Dn AE 1 | |
08 Jun 2023 | PWD Tarring work pending | Piravom Project Dn AE 1 | |
05 Jun 2023 | PWD Tarring work pending | Piravom Project Dn AE 1 | |
29 May 2023 | Pipe laying through PWD road is completed. Due to heavy summer rain road restoration work cannot be completed. | Piravom Project Dn AE 1 | |
16 Aug 2022 | Pipe laying through PWD road is completed. Due to heavy summer rain road restoration work cannot be completed. | Kattappana Project Dn EE | |
15 Aug 2022 | Pipe laying through PWD road is completed. Due to heavy summer rain road restoration work cannot be completed. | Kattappana Project Dn EE | |
11 Jul 2022 | Road restoration work through main road to be completed afteer monsoon | Kattappana Project Dn EE | |
28 May 2022 | Pipe laying through PWD road also completed | Kattappana Project Dn EE | |
16 Apr 2022 | Pipe laying through Pandyanpara Maneed PWD road in progress | Kattappana Project Dn EE | |
17 Mar 2022 | NOC for road cutting from PWD roads obtained on 16.03.2022 | Kattappana Project Dn EE |