WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m

Project WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m
Project Code EKMKIIFB0119520
Type Main project
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
AS Amount (Rs) 18207000
AS Number TRAN 2- WRD 005-126-PA-01/KIIFB
TS Amount (Rs) 15200000
TS Number TS/2019-20/2019/10992 dt 30/10/2019
Total Bill Submitted (Rs) 6920000
Total Bill Paid (Rs) 6920000
Population Benefitted 12500
Capacity in MLD 9.00
Actual Project Completion Date Date is not specified
Coverage UWSS to Piravom Municipalty(part)
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m Project Division Piravom(Kattapana)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
24 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
17 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
11 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
04 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/12/2019
Scheduled date of Completion of the Project 30 Jun 2022
Expected date of Completion 30/10/2022

Processing Dates

AS Date 19 Jan 2019
TS Date 30 Oct 2019

Other details

Project Officers View