- Home
- WRD005-126-UWSS to Piravom and adjoining...
WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m
Project |
WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m |
Project Code |
EKMKIIFB0119520 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
18207000
|
AS Number |
TRAN 2- WRD 005-126-PA-01/KIIFB |
TS Amount (Rs) |
15200000 |
TS Number |
TS/2019-20/2019/10992 dt 30/10/2019 |
Total Bill Submitted (Rs) |
6920000 |
Total Bill Paid (Rs) |
6920000 |
Population Benefitted |
12500 |
Capacity in MLD |
9.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
UWSS to Piravom Municipalty(part) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
WRD005-126-UWSS to Piravom and adjoining panchayaths- Replacement of damaged 250 mm AC gravity main from Kakkadu WTP to Pazhoor sump by laying 250 mm DI pipe line 2650 m |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 |
Piravom Project Dn AE 1 |
|
24 Aug 2023 |
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 |
Piravom Project Dn AE 1 |
|
17 Aug 2023 |
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 |
Piravom Project Dn AE 1 |
|
11 Aug 2023 |
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 |
Piravom Project Dn AE 1 |
|
04 Aug 2023 |
The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 |
Piravom Project Dn AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
31/12/2019 |
Scheduled date of Completion of the Project |
30 Jun 2022 |
Expected date of Completion |
30/10/2022 |
Processing Dates
AS Date |
19 Jan 2019 |
TS Date |
30 Oct 2019 |