Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
24 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
17 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
11 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
04 Aug 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
29 Jul 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
18 Jul 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
06 Jul 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
30 Jun 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1
26 Jun 2023 The remaining works in this contract are 1.Road restoration for a length of 120m to BM&BC standered as per KIIFB norms. 2.Providing 200mm Mechanical flow meter at TP yard Kakkad. 3.Construction of flow meter chamber with Manhole cover. For the balance works an estimate is prepared and is proposed to arrange the work at the risk and cost of the contractor Sri.M BPradeep after terminating the contract.The total estimate cost comes to Rs.419000.00 Piravom Project Dn AE 1