15 Jun 2021 67% completed, 1319 FHTC provided. Irinjalakkuda PH Dn EE
10 Jun 2021 67% completed, 1319 FHTC provided. Irinjalakkuda PH Dn EE
01 Jun 2021 67% completed, 1319 FHTC provided. Irinjalakkuda PH Dn EE
30 May 2021 67% completed, 1319 FHTC provided. Irinjalakkuda PH Dn EE
23 May 2021 67% completed, 1319 FHTC provided. Irinjalakkuda PH Dn EE
17 May 2021 67% completed, 1319 FHTC provided. Irinjalakkuda PH Dn EE
05 May 2021 67% completed, 1319 FHTC provided.- Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes Irinjalakkuda PH Dn EE
23 Mar 2021 CC 5th & part bill of 127nos FHTC submitted to Division Irinjalakkuda PH Dn EE
18 Mar 2021 Total FHTCs tagged as on 17.03.2021 =1235 Nos Irinjalakkuda PH Dn EE
18 Mar 2021 1102 FHTCs billed so far Irinjalakkuda PH Dn EE