- Home
- Jal Jeevan Mission- Kodakara Grama Panch...
Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes
Project |
Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes |
Project Code |
TCRJJM07203797 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC,
Retrofitting and Augmentation of Existing Rural Water Supply Schemes |
Status |
On-going |
District |
Thrissur |
Executing Office |
Chalakkudy PH Sn |
AS Amount (Rs) |
38000000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
34000000 |
TS Number |
TS/2020-2021/2020/13327 |
Total Bill Submitted (Rs) |
33566679 |
Total Bill Paid (Rs) |
33566679 |
Population Benefitted |
7900 |
Capacity in MLD |
3.60 |
Actual Project Completion Date |
22 Jun 2022 |
Coverage |
Kodakara, Kavumthara, Vallapady marathampillyand Kuzhikani areas , Puliparakunnu and kalanagar areas |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission - 2020-21- Supply and installation of Water purifier with Multiple purification by UV process Filteration unit to various Anganwadies in Kodakara Grama Panchayath under WSP Section No.I Chalakudy |
Chalakkudy PH Sn |
|
2 |
Jal Jeevan Mission (JJM)-Kodakara Grama Panchayath (Phase 1)- Feeder line from Vattekkad to Perambra and near hotel Varsha Kodakara to Marathampilly in Kodakara Grama panchayath-Pipeline Work |
Chalakkudy PH Sn |
|
3 |
Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes |
Chalakkudy PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Aug 2022 |
Final bill submitted to Dn. 1988 FHTCs given totally. |
Chalakudy AEE |
|
28 Feb 2022 |
work completed |
Chalakudy AE 1 |
|
22 Feb 2022 |
work completed |
Chalakudy AE 1 |
|
01 Feb 2022 |
99% completed |
Chalakudy AE 1 |
|
12 Jan 2022 |
99% completed |
Chalakudy AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
31/10/2020 |
Scheduled date of Completion of the Project |
30 Jun 2022 |
Expected date of Completion |
16/02/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
05 Sep 2020 |