Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes

Project Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes
Project Code TCRJJM07203797
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes
Status On-going
District Thrissur
Executing Office Chalakkudy PH Sn
AS Amount (Rs) 38000000
AS Number G.O.(Rt)No.541/2020/WRD
TS Amount (Rs) 34000000
TS Number TS/2020-2021/2020/13327
Total Bill Submitted (Rs) 33566679
Total Bill Paid (Rs) 33566679
Population Benefitted 7900
Capacity in MLD 3.60
Actual Project Completion Date 22 Jun 2022
Coverage Kodakara, Kavumthara, Vallapady marathampillyand Kuzhikani areas , Puliparakunnu and kalanagar areas
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission - 2020-21- Supply and installation of Water purifier with Multiple purification by UV process Filteration unit to various Anganwadies in Kodakara Grama Panchayath under WSP Section No.I Chalakudy Chalakkudy PH Sn
2 Jal Jeevan Mission (JJM)-Kodakara Grama Panchayath (Phase 1)- Feeder line from Vattekkad to Perambra and near hotel Varsha Kodakara to Marathampilly in Kodakara Grama panchayath-Pipeline Work Chalakkudy PH Sn
3 Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes Chalakkudy PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Aug 2022 Final bill submitted to Dn. 1988 FHTCs given totally. Chalakudy AEE
28 Feb 2022 work completed Chalakudy AE 1
22 Feb 2022 work completed Chalakudy AE 1
01 Feb 2022 99% completed Chalakudy AE 1
12 Jan 2022 99% completed Chalakudy AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/10/2020
Scheduled date of Completion of the Project 30 Jun 2022
Expected date of Completion 16/02/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 05 Sep 2020

Other details

Project Officers View