Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Jul 2021 | CC VII th & Part bill submitted to Division Office. on 16.07.2021 | Irinjalakkuda PH Dn EE | |
20 Jul 2021 | 78% completed | Irinjalakkuda PH Dn EE | |
08 Jul 2021 | 77% completed, 1524 FHTC provided. | Irinjalakkuda PH Dn EE | |
06 Jul 2021 | 69% completed, 1370 FHTC provided. | Irinjalakkuda PH Dn EE | |
05 Jul 2021 | 69% completed, 1370 FHTC provided. | Irinjalakkuda PH Dn EE | |
02 Jul 2021 | 69% completed, 1370 FHTC provided. | Irinjalakkuda PH Dn EE | |
29 Jun 2021 | 69% completed, 1370 FHTC provided. | Irinjalakkuda PH Dn EE | |
25 Jun 2021 | 69% completed, 1370 FHTC provided. | Irinjalakkuda PH Dn EE | |
23 Jun 2021 | 67% completed, 1319 FHTC provided. | Irinjalakkuda PH Dn EE | |
21 Jun 2021 | 67% completed, 1319 FHTC provided. | Irinjalakkuda PH Dn EE |